Jinan Housing and Urban-Rural Development Bureau Emergency Notice on Strengthening Work Safety in Building Construction
Release time:
2022-10-13
Source:
Jinan Housing and Urban-Rural Development Bureau
Emergency Notice on Strengthening Safe Production in Building Construction
Housing and Urban-Rural Development Bureau of all districts and counties, Construction Management Department of Jinan New Old Energy Conversion Starting Area Management Committee, Construction Management Department of Jinan High-tech Zone Management Committee, Planning and Development Bureau of Nanfangshan Mountain Management Committee, and all relevant units:
In order to implement the requirements of production safety work at all levels, further strengthen the city's construction safety work in the field of construction, and strengthen the system of responsibility for production safety work, according to the "establish a special team, grasp the two lines of supervision, and fight three battles" work idea, highlighting the "implementation of the primary responsibility of the construction unit, In accordance with the working idea of "setting up a special team to supervise two lines and fight three battles", highlighting the two key points of "implementing the primary responsibility of the construction unit, the main responsibility of the construction general contracting unit" and "reinforcing the supervision of the departments and enterprises", we will implement the responsibility and improve the working mechanism to ensure the implementation of the production safety management measures to ensure that we can achieve the goal of winning the fourth quarter.
The relevant matters are notified as follows.
First, the establishment of a task force
(A) the establishment of the project production safety task force
Starting immediately, the city's projects under construction are to establish production safety task force, task force led by the construction unit, the general contracting unit, the relevant subcontracting units, supervision units together, the construction unit as the head of the task force.
The person in charge of the task force by the construction unit.
(ii) Duties of the task force
1. each project team combined with the actual development of the corresponding work system, fully responsible for the project's production safety work, including daily morning meeting for the day's safety arrangements for the day, the construction process of production safety supervision and inspection, safety and hidden danger investigation and rectification, and every day on the safety of production work to summarize and fill out a work log.
Production work to summarize and fill out the work log (see annex).
2. The task force designated a person responsible for the task force to check the implementation of the work, improve the task force log file, daily responsible for the work log photo uploaded to the project through WeChat.
The work team will hold weekly meetings.
3. The task force will hold a regular meeting once a week to summarize the production safety work for the week and set up the production safety focus for the next week.
Summarize the work of production safety for the week and set up the key tasks of production safety for the next week.
Second, grasp the two lines of supervision
(a) Daily supervision and management of the supervisory body
Strengthen the supervision body's responsibility for production safety, the city, district and county levels of construction departments and supervision bodies should be in accordance with the responsibilities of the site to grasp the guidance and supervision, increase supervision and frequency.
Frequency of supervision. Strengthen the supervision and inspection of construction projects by adopting the method of "four no two straight" and "sweeping the road".
The company will strengthen the supervision and inspection of engineering projects by adopting the "four no two straight" and "sweeping the road" methods, implement differentiated supervision measures, carry out high-frequency supervision and inspection of production safety accident-prone areas, key enterprises and large-scale projects, and promptly supervise and rectify problems and hidden dangers found, and supervise and deal with major hidden dangers, so as to ensure that all safety tasks and measures are implemented and put into practice.
All major hidden problems are put under supervision to ensure that all production safety tasks and measures are implemented.
(ii) Supervision and management of the main body of the general contracting company
(i) To strengthen the production safety responsibility of general contractors, the person in charge of production safety or the person in charge of the safety management organization of general contractors will regularly go down to the project, at least once a week, to help the project improve and optimize the system of responsibility for production safety, make up for the shortcomings and check the loopholes, supervise and guide the project and the work team to implement the dual prevention mechanism for production safety, strengthen the control of major sources of danger and the investigation and management of major hidden dangers of accidents, and eliminate hidden dangers of production safety accidents in a timely manner. and supervise the implementation of corrective measures.
Implement corrective measures.
III. Fighting three battles
(a) Fighting the "October Battle"
Half of the time in October, the districts and counties housing and construction departments combined with housing and building construction to prevent falls from a height special rectification of the 100 days of action to carry out timely safety inspections, the construction site carpet inspection, focusing on investigation and remediation of the parties involved in all kinds of illegal and irregular behavior, all kinds of safety hazards at the construction site, the parties involved in the construction of the person in charge of the duty in the position, the bitter battle for half a month to ensure that the situation of safety in production in October is stable and good, for the 20th National Congress held in the city, to ensure that the production safety situation is stable and good, to ensure the safety of the construction site. good, for the twentieth session of the General Assembly
Create a safe and stable environment for the 20th National Congress.
(II) Fight the "winter construction war".
November into the winter construction, according to the characteristics of winter construction, and effectively implement the prevention of wind, collapse, prevention of
According to the characteristics of winter construction, safety measures against wind, collapse, electric shock, fall, fire, poisoning and other safety measures should be effectively implemented; in the event of extreme weather conditions such as heavy storms and snow, outdoor construction work should be stopped immediately, and illegal behaviors such as rushing to meet deadlines and working in contravention of regulations should be resolutely avoided. The construction units should focus on "zero accidents, a prevention and control, two non-stop" to strengthen the work measures, the integration of production safety, epidemic prevention and control, dust management trinity synchronization, and strive to ensure that November continue to maintain a steady improvement in safety and production.
(c) To fight for the safety of production
(C) Playing a good "year-end closing battle"
December facing the end of the year, and at the time of winter construction, by low temperatures, gusty winds, rain and snow and other inclement weather, coupled with the end of the year, the project rush to catch up with the time nodes, the safety management difficulties increase, is very prone to cause production and safety accidents. Municipal, district and county housing construction departments should seriously fulfill the departmental supervision responsibility, the construction units should strictly implement the responsibility of enterprise production safety, resolutely overcome paralysis and fluke, formulate practical safety precautionary programs, take multiple measures and give full play to the role of project safety team, and make every effort to ensure that the safety situation before the end of the year is stable, good and stable.
The situation of safety and production before the end of the year will continue to be stable and good, so as to realize a perfect ending.
Work requirements
(A) supervision and inspection. Municipal, district and county supervisory bodies on a regular basis from time to time on the project safety task force to perform their duties as well as the project manager, full-time safety officer on duty in the situation of inspection and random checks, the implementation of "one day, one table" implementation of the duties of the task force has not been implemented, the project manager and the full-time safety officer did not show up to perform their duties, do not fill out the logbook of the project are all
Work will be stopped until the rectification is completed and reviewed before resumption of work.
(ii) Summarize the notification. Municipal, district and county supervision agencies every Friday will check and
City, district and county supervision agencies every Friday will check and dispatch the project safety task force establishment, operation and other inspection and supervision of the report to the Municipal Engineering Quality and Safety Center. The Municipal Housing and Urban-Rural Development Bureau will conduct a weekly inspection of the situation.
Contact: Tang Chunkai, Tel: 61378700.
Related News
In order to thoroughly implement the spirit of the twentieth CPC National Congress, focusing on carbon peak carbon and related deployments, accelerate the urban and rural construction of green low-carbon transformation and development, according to "the province's housing and urban-rural construction system key projects" focus on the "dual-carbon" goal of gathering new construction "innovation and excellence According to the "Provincial Housing and Urban-Rural Construction System Key Project "Focus on 'Double Carbon' Target Gathering New Construction" Innovation and Excellence Labor Competition Implementation Plan"
In order to standardize and unify the construction engineering architecture, structure, professional fire technical standards for the implementation of the scale, and further enhance the level of fire protection design review and acceptance of construction projects, to protect the province's fire protection quality and safety of construction projects, the Provincial Department of Housing and Urban-Rural Development, the organization of the relevant units to prepare the "Shandong Province, fire protection design review and acceptance of construction projects technical guidelines (architecture, structure)", has been examined and approved by the experts, and is hereby issued to you from the date of issuance of It has been reviewed and approved by experts and is hereby issued to you, and shall come into force from the date of its issuance.
In order to promote the prevention and control of the new crown pneumonia epidemic and economic and social development in an integrated manner, and to support the relevant enterprises and practitioners to resume work and production, it was decided to make the following adjustments to the validity period of the "Certificate of Competence for Job Training and Assessment of Professionals in the Field of Housing and Urban-Rural Development" (hereinafter referred to as the certificate for on-site professionals) and the "Certificate of Competence for Professional Training and Assessment of Practitioners in Gas Business Enterprises"
The Ministry of Housing and Urban-Rural Development has decided to amend the Measures for the Administration of Permits for the Discharge of Urban Sewage into Drainage Pipe Networks (Order No. 21 of the Ministry of Housing and Urban-Rural Development) as follows.
Municipal Housing and Urban-Rural Development Bureau, Urban Management Bureau, Jinan, Qingdao, Zibo, Zaozhuang, Dongying, Jining, Weihai, Binzhou, Heze Municipal Water (Water Resources) Bureau, Jinan, Qingdao Municipal Gardening and Forestry (Greening) Bureau, Jinan Urban and Rural Transportation Bureau: Now the "Shandong Province building construction safety and civilization standardization site management measures" issued to you, please combine with the actual implementation.